Short answer: a 4 inch compacted gravel base takes 1.23 cubic yards (about 1.7 tons) per 100 square feet, so order about 1.9 tons once you add 10% for compaction. A 6 inch base takes 2.85 tons per 100 square feet with the same allowance. Below are order amounts for 12 patio and walkway sizes, the sand bed, and how deep to dig.
How we worked this out
Every number on this page comes from the same formulas our paver calculator uses, run in Python:
Base (tons) = cubic yards × 1.4
Sand (cu yd) = area (sq ft) × sand depth (in) ÷ 12 ÷ 27
Sand (tons) = cubic yards × 1.35
The assumptions behind them:
- Density: 1.4 tons per cubic yard for gravel base and 1.35 for bedding sand, the calculator's defaults. Our gravel calculator lists crusher run (road base) at 1.45 and #57 stone at 1.42. Your quarry's figure can differ, and wet stone weighs more.
- Compaction: the depth you enter is the finished, compacted depth. Loose gravel settles when you run a plate compactor over it, so the order columns below add 10%. The calculator shows the compacted volume and tells you to add the 10% yourself.
- Sand bed: 1 inch of coarse concrete sand, the calculator default. The sand is screeded flat and not compacted before the pavers go down, so no allowance is added to it.
- Area: the paver area only. If you run the base past the edges (see below), use the bigger footprint.
Gravel base per 100 square feet, by depth
Use this as a per-unit chart. A 250 sq ft patio needs 2.5 times the row for its depth.
| Compacted depth | Cubic feet | Cubic yards | Tons | Order with 10% | Sq ft per ton |
|---|---|---|---|---|---|
| 3 in | 25.0 | 0.93 | 1.30 | 1.02 cu yd / 1.43 tons | 77 |
| 4 in (patios, walkways) | 33.3 | 1.23 | 1.73 | 1.36 cu yd / 1.90 tons | 58 |
| 5 in | 41.7 | 1.54 | 2.16 | 1.70 cu yd / 2.38 tons | 46 |
| 6 in (clay or wet soil) | 50.0 | 1.85 | 2.59 | 2.04 cu yd / 2.85 tons | 39 |
| 8 in (driveways) | 66.7 | 2.47 | 3.46 | 2.72 cu yd / 3.80 tons | 29 |
| 10 in | 83.3 | 3.09 | 4.32 | 3.40 cu yd / 4.75 tons | 23 |
| 12 in | 100.0 | 3.70 | 5.19 | 4.07 cu yd / 5.70 tons | 19 |
"Sq ft per ton" is the compacted coverage of one ton at that depth, before the 10% allowance. Each extra inch of base adds 0.31 cubic yards, or about 0.43 tons, per 100 sq ft.
What to order for common patio and walkway sizes
Gravel columns include the 10% compaction allowance. The sand column is a 1 inch bed with no allowance.
| Size | Area | 4 in base, order | 6 in base, order | 1 in sand bed |
|---|---|---|---|---|
| 3 × 20 ft walkway | 60 sq ft | 0.81 cu yd / 1.14 tons | 1.22 cu yd / 1.71 tons | 0.19 cu yd / 0.25 tons |
| 8 × 10 ft | 80 sq ft | 1.09 cu yd / 1.52 tons | 1.63 cu yd / 2.28 tons | 0.25 cu yd / 0.33 tons |
| 10 × 10 ft | 100 sq ft | 1.36 cu yd / 1.90 tons | 2.04 cu yd / 2.85 tons | 0.31 cu yd / 0.42 tons |
| 10 × 12 ft or 4 × 30 ft walkway | 120 sq ft | 1.63 cu yd / 2.28 tons | 2.44 cu yd / 3.42 tons | 0.37 cu yd / 0.50 tons |
| 12 × 12 ft | 144 sq ft | 1.96 cu yd / 2.74 tons | 2.93 cu yd / 4.11 tons | 0.44 cu yd / 0.60 tons |
| 12 × 16 ft | 192 sq ft | 2.61 cu yd / 3.65 tons | 3.91 cu yd / 5.48 tons | 0.59 cu yd / 0.80 tons |
| 14 × 14 ft | 196 sq ft | 2.66 cu yd / 3.73 tons | 3.99 cu yd / 5.59 tons | 0.60 cu yd / 0.82 tons |
| 16 × 16 ft | 256 sq ft | 3.48 cu yd / 4.87 tons | 5.21 cu yd / 7.30 tons | 0.79 cu yd / 1.07 tons |
| 16 × 20 ft | 320 sq ft | 4.35 cu yd / 6.08 tons | 6.52 cu yd / 9.13 tons | 0.99 cu yd / 1.33 tons |
| 20 × 20 ft | 400 sq ft | 5.43 cu yd / 7.60 tons | 8.15 cu yd / 11.41 tons | 1.23 cu yd / 1.67 tons |
| 20 × 24 ft | 480 sq ft | 6.52 cu yd / 9.13 tons | 9.78 cu yd / 13.69 tons | 1.48 cu yd / 2.00 tons |
Suppliers sell by the ton or by the cubic yard, often in half-yard or half-ton steps, so round up to the next step they sell. For the paver count itself, see how many pavers for a 12x12 patio.
How deep to dig
The hole has to hold the base, the sand and the paver itself. The table assumes a 2 3/8 inch (60 mm) paver, a common patio thickness. Check the thickness of yours and add or subtract the difference. "Soil to remove" is the volume of the hole, which is roughly what you will haul away or spread elsewhere (dug soil also fluffs up and takes more room in a trailer than it did in the ground).
| Base | Total dig depth | Soil to remove per 100 sq ft | 12 × 12 ft | 16 × 16 ft | 20 × 20 ft |
|---|---|---|---|---|---|
| 4 in | 7 3/8 in | 2.28 cu yd | 3.28 cu yd | 5.83 cu yd | 9.10 cu yd |
| 6 in | 9 3/8 in | 2.89 cu yd | 4.17 cu yd | 7.41 cu yd | 11.57 cu yd |
| 8 in | 11 3/8 in | 3.51 cu yd | 5.06 cu yd | 8.99 cu yd | 14.04 cu yd |
If the finished patio should sit above the lawn, subtract that height from the dig depth. If it must slope away from the house for drainage, the dig is deeper at the low end.
Worked example: a 12 × 16 ft patio on clay soil
The yard has heavy clay, so you plan a 6 inch base instead of 4.
- Area: 12 × 16 = 192 sq ft.
- Base volume: 192 × 6 ÷ 12 = 96 cubic feet. 96 ÷ 27 = 3.56 cubic yards compacted.
- Base weight: 3.56 × 1.4 = 4.98 tons.
- Add 10% for compaction: 3.91 cubic yards, or 5.48 tons. Order 5.5 tons.
- Sand bed: 192 × 1 ÷ 12 ÷ 27 = 0.59 cubic yards × 1.35 = 0.80 tons.
- Dig depth: 6 + 1 + 2 3/8 = 9 3/8 inches, which removes 192 × 9.375 ÷ 12 ÷ 27 = 5.56 cubic yards of soil.
In the calculator, enter 16 × 12 ft, base depth 6 in, sand 1 in. It shows 3.56 cu yd (4.98 tons) of base and 0.59 cu yd (0.80 tons) of sand; the 10% on the base is the step you add. On normal, well-drained soil with a 4 inch base, the same patio needs 3.65 tons to order, so the clay costs you about 1.8 extra tons of stone.
What changes the answer
- Base depth. The biggest lever. Going from 4 to 6 inches on the 12 × 16 ft patio raises the order from 3.65 to 5.48 tons, which is 50% more stone.
- Running the base past the edges. Many installers extend the base beyond the pavers so the edge restraint sits on compacted gravel. Extending it 6 inches on every side turns 12 × 16 into a 13 × 17 ft footprint (221 sq ft), and the 6 inch order grows from 5.48 to 6.30 tons.
- Material density. Crusher run at 1.45 tons per cubic yard instead of 1.4 takes the same 12 × 16 ft, 6 inch order from 5.48 to 5.67 tons. The cubic yards do not change, only the weight.
- Sand depth. A 1.5 inch bed instead of 1 inch on 192 sq ft takes the sand from 0.80 to 1.20 tons. Thicker sand also tends to shift under the pavers, so more is not better here.
- Price. The calculator multiplies total tons by your price per ton. At an example price of $45 per ton (the placeholder in the calculator, not a quote), 5.48 tons of base is about $246, and with the 0.80 tons of sand about $282 before delivery. Ask your supplier for the real figure and the delivery fee.
Buying bagged base instead of bulk
For a small walkway, bags can be easier than a truck. Read the cubic feet on the bag: a cubic yard is 27 cubic feet, so it takes 54 bags of 0.5 cubic feet to make one yard. A 10 × 10 ft patio with a 4 inch base needs 33.3 cubic feet compacted, or 67 of those bags, and about 74 with the 10% allowance. The 1 inch sand bed adds 17 bags. Past about 100 sq ft, bulk delivery is usually the simpler option.
Common mistakes
- Ordering the compacted volume. The tables in most charts, and the calculator's result, are the finished depth. Without the extra 10% you run short on the last strip.
- Mixing up cubic feet and cubic yards. 33 cubic feet is 1.23 cubic yards, not 33. Divide cubic feet by 27.
- Using pea gravel or round river rock as the base. Round stones roll and do not lock together under a compactor. Use angular crushed stone with fines (crusher run, road base, or a product sold as paver base).
- Compacting it all at once. The calculator page suggests compacting in 2 inch lifts. A 6 inch base is three passes, not one.
- Forgetting the paver thickness in the dig. Digging only to the base depth leaves the finished surface sitting 3 inches above where you wanted it.
Honest limits
These are planning numbers, not an engineered design. Density changes by quarry and moisture, and the 10% compaction allowance is a rule of thumb; some crushed stone settles more. The calculator does not model frost depth, geotextile fabric under the base, or soft spots that need extra digging. For a driveway or a patio on poorly drained ground, follow the base depth the paver maker or your local building office gives. For gravel under a driveway without pavers, see how much gravel for a driveway.
Try the paver calculator
Enter your own numbers below, or open the full paver calculator with the formula and more examples.
This guide is general information with example numbers, not financial, tax or building advice. Your costs and results will differ. Terms
Frequently asked questions
How much gravel do I need under pavers?
For a patio or walkway, plan a 4 inch compacted gravel base: 1.23 cubic yards, about 1.7 tons, per 100 square feet. Order about 1.9 tons per 100 square feet to allow 10% for compaction.
How many tons of gravel for a 12x12 paver patio?
A 12 x 12 ft patio is 144 square feet. A 4 inch base is 1.78 cubic yards compacted, about 2.5 tons, so order about 2.74 tons. With a 6 inch base, order about 4.1 tons.
How deep should the gravel be under pavers?
About 4 inches compacted for patios and walkways, 6 inches on clay or wet soil, and 6 to 8 inches for driveways, with a 1 inch sand bed on top.
How much sand do I need under pavers?
A 1 inch bed takes 0.31 cubic yards, about 0.42 tons, per 100 square feet. A 12 x 12 ft patio needs about 0.6 tons.
How deep do I dig for pavers?
Add the base, the sand and the paver thickness. With a 4 inch base, 1 inch of sand and a 2 3/8 inch paver, dig 7 3/8 inches. With a 6 inch base, dig 9 3/8 inches.
How many square feet does a ton of gravel cover under pavers?
At 1.4 tons per cubic yard, one ton covers about 58 square feet at 4 inches compacted and about 39 square feet at 6 inches.