How Many Yards of Concrete Do I Need?

Short answer: one cubic yard of concrete covers 81 sq ft at 4 inches thick, 65 sq ft at 5 inches and 54 sq ft at 6 inches. A 12x12 patio at 4 inches needs about 2 yards with 10% waste, a 24x24 garage slab about 7.8 yards, and a thickened edge around that garage adds another 2.5 yards.

How we worked this out

Every number on this page comes from the formulas in our concrete calculator, run for each size in the tables:

Slab: length (ft) × width (ft) × thickness (in) ÷ 12 = cubic feet
Footing: length (ft) × width (in) ÷ 12 × depth (in) ÷ 12 = cubic feet
Round pier: π × (diameter in ÷ 24)² × depth (in) ÷ 12 = cubic feet
Cubic yards = cubic feet × 1.10 ÷ 27

The assumptions behind the tables:

How much area one yard of concrete covers

This is the chart to keep on your phone. Divide 27 by the thickness in feet and you get the square feet one yard fills, before waste:

ThicknessSq ft per cubic yardTypical use
3 in108Overlay or thin pad, not a structural slab
3.5 in92.6Slab formed with 2×4s on edge (actual 3.5 in)
4 in81Patio, sidewalk, shed floor
5 in64.8Car driveway
6 in54Heavy vehicle driveway, hot tub pad
8 in40.5Heavy equipment pad

Every extra inch on a 4 inch slab adds 25% more concrete. That is why the thickness you measure matters more than a few inches of length.

Cubic yards for common slab sizes

All figures include 10% waste. The last column is the same 4 inch slab with no waste, so you can see exactly what the allowance adds.

Slab4 in5 in6 in4 in, no waste
10 × 10 ft1.361.702.041.23
10 × 12 ft1.632.042.441.48
12 × 12 ft1.962.442.931.78
12 × 16 ft2.613.263.912.37
12 × 20 ft3.264.074.892.96
16 × 20 ft4.355.436.523.95
20 × 20 ft5.436.798.154.94
12 × 40 ft (driveway)6.528.159.785.93
24 × 24 ft (2 car garage)7.829.7811.737.11
24 × 30 ft9.7812.2214.678.89
20 × 40 ft (double driveway)10.8613.5816.309.88
30 × 30 ft12.2215.2818.3311.11
4 × 50 ft (sidewalk)2.723.404.072.47

Ready-mix plants sell in fixed steps and many have a minimum load, so round the figure up to whatever increment your supplier quotes. Ask them when you call; it changes the last fraction of a yard, not the size of the job.

Footings and piers

Long narrow pours are easier to think about per length of trench. With 10% waste:

Footing width × depthYards per 10 ftYards per 100 ftFeet of footing per yard (no waste)
12 × 8 in0.272.7240.5
16 × 8 in0.363.6230.4
16 × 10 in0.454.5324.3
20 × 10 in0.575.6619.4
24 × 12 in0.818.1513.5

Footing sizes for a house or an addition are set by your local building code and soil, so use these rows to estimate volume once you know the required size, not to choose it.

Deck and porch piers poured in round tube forms are small, so they are usually bought in bags. Each row is one pier with 10% waste; "piers per yard" is useful if you are pouring many from a truck.

Tube diameter × depthCu ft per pier80 lb bags per pierPiers per cubic yard (no waste)
8 × 36 in1.15225.8
8 × 48 in1.54319.3
10 × 36 in1.80316.5
10 × 48 in2.40412.4
12 × 36 in2.59511.5
12 × 48 in3.4668.6
16 × 36 in4.6186.4
16 × 48 in6.14114.8
18 × 48 in7.78133.8

Pier depth must reach below the frost line where you live, so 48 in rows are common in cold climates. If you also need posts, rails and pickets, the fence calculator counts the post concrete with the rest of the fence.

Worked example: a garage slab with a thickened edge

A 24 × 24 ft garage slab, 4 inches thick, with a thickened edge around the outside: a strip 12 inches wide where the slab goes down to 12 inches deep, so 8 inches below the main slab. The edge size here is only an example; your plans or inspector set the real one.

  1. Main slab: 24 × 24 × 4 ÷ 12 = 192 cubic feet.
  2. Edge strip area: the outer 24 × 24 square minus the inner 22 × 22 square = 576 - 484 = 92 sq ft. Using the outside perimeter (96 ft) would count the four corners twice.
  3. Extra edge concrete: 92 sq ft × 8 ÷ 12 = 61.3 cubic feet. In the calculator this is the footing shape: 92 ft long, 12 in wide, 8 in deep.
  4. Total: 192 + 61.3 = 253.3 cubic feet, or 9.38 cubic yards with no waste.
  5. Add 10%: 278.7 cubic feet, which is 10.32 cubic yards. With 5% it would be 9.85.

So the thickened edge alone adds 2.27 yards before waste (2.5 with it), about a third more than the flat slab. Order about 10.5 yards, or round up to your supplier's next step. By hand it would be 465 bags of 80 lb mix, which is why nobody bags a garage floor.

What changes the answer

Common mistakes

Try the concrete calculator

Enter your own numbers below, or open the full concrete calculator with the formula and more examples.

This guide is general information with example numbers, not financial, tax or building advice. Your costs and results will differ. Terms

Frequently asked questions

How many square feet does a yard of concrete cover?

At 4 inches thick, one cubic yard covers 81 sq ft. At 5 inches it covers 64.8 sq ft and at 6 inches 54 sq ft, before any waste allowance.

How many yards of concrete do I need for a 24x24 garage?

About 7.1 cubic yards for a 4 inch slab, or 7.8 with 10% waste. At 6 inches it is about 11.7 yards with waste. A thickened edge 12 inches wide and 8 inches deeper adds about 2.3 yards more before waste.

How many yards of concrete for a 12x12 slab?

A 12x12 slab at 4 inches thick needs 1.78 cubic yards, or about 1.96 with 10% waste. At 6 inches it needs about 2.93 yards with waste.

How do I calculate yards of concrete?

Multiply length by width in feet, multiply by the thickness in inches and divide by 12 to get cubic feet. Add your waste allowance (usually 10%), then divide by 27 to get cubic yards.

How many yards of concrete for a 100 ft footing?

A 16 inch wide, 8 inch deep footing takes about 3.6 cubic yards per 100 ft with 10% waste. A 20 by 10 inch footing takes about 5.7 yards.