How Many Yards of Concrete Do I Need?
Short answer: one cubic yard of concrete covers 81 sq ft at 4 inches thick, 65 sq ft at 5 inches and 54 sq ft at 6 inches. A 12x12 patio at 4 inches needs about 2 yards with 10% waste, a 24x24 garage slab about 7.8 yards, and a thickened edge around that garage adds another 2.5 yards.
How we worked this out
Every number on this page comes from the formulas in our concrete calculator, run for each size in the tables:
Footing: length (ft) × width (in) ÷ 12 × depth (in) ÷ 12 = cubic feet
Round pier: π × (diameter in ÷ 24)² × depth (in) ÷ 12 = cubic feet
Cubic yards = cubic feet × 1.10 ÷ 27
The assumptions behind the tables:
- A cubic yard is 27 cubic feet (3 ft × 3 ft × 3 ft).
- 10% waste is added to every figure unless a row says otherwise. That is the calculator's default and covers spillage, forms that bow outward and a base that is not perfectly flat. If your base is laser-level and compacted, 5% is enough; the effect of that choice is shown further down.
- Thickness is the real depth of the form, measured in several places, not the nominal board size.
- Bag counts use the yields printed on typical premixed bags, the same ones the calculator uses: 0.60 cu ft for an 80 lb bag, 0.45 for 60 lb and 0.30 for 40 lb.
- Ready-mix prices vary a lot by region and season, so this page does not quote one. Where we compare bags with a truck, we use the calculator's example prices ($165 a yard and $6.50 an 80 lb bag) and say so. Put your own quotes into the calculator before you decide.
How much area one yard of concrete covers
This is the chart to keep on your phone. Divide 27 by the thickness in feet and you get the square feet one yard fills, before waste:
| Thickness | Sq ft per cubic yard | Typical use |
|---|---|---|
| 3 in | 108 | Overlay or thin pad, not a structural slab |
| 3.5 in | 92.6 | Slab formed with 2×4s on edge (actual 3.5 in) |
| 4 in | 81 | Patio, sidewalk, shed floor |
| 5 in | 64.8 | Car driveway |
| 6 in | 54 | Heavy vehicle driveway, hot tub pad |
| 8 in | 40.5 | Heavy equipment pad |
Every extra inch on a 4 inch slab adds 25% more concrete. That is why the thickness you measure matters more than a few inches of length.
Cubic yards for common slab sizes
All figures include 10% waste. The last column is the same 4 inch slab with no waste, so you can see exactly what the allowance adds.
| Slab | 4 in | 5 in | 6 in | 4 in, no waste |
|---|---|---|---|---|
| 10 × 10 ft | 1.36 | 1.70 | 2.04 | 1.23 |
| 10 × 12 ft | 1.63 | 2.04 | 2.44 | 1.48 |
| 12 × 12 ft | 1.96 | 2.44 | 2.93 | 1.78 |
| 12 × 16 ft | 2.61 | 3.26 | 3.91 | 2.37 |
| 12 × 20 ft | 3.26 | 4.07 | 4.89 | 2.96 |
| 16 × 20 ft | 4.35 | 5.43 | 6.52 | 3.95 |
| 20 × 20 ft | 5.43 | 6.79 | 8.15 | 4.94 |
| 12 × 40 ft (driveway) | 6.52 | 8.15 | 9.78 | 5.93 |
| 24 × 24 ft (2 car garage) | 7.82 | 9.78 | 11.73 | 7.11 |
| 24 × 30 ft | 9.78 | 12.22 | 14.67 | 8.89 |
| 20 × 40 ft (double driveway) | 10.86 | 13.58 | 16.30 | 9.88 |
| 30 × 30 ft | 12.22 | 15.28 | 18.33 | 11.11 |
| 4 × 50 ft (sidewalk) | 2.72 | 3.40 | 4.07 | 2.47 |
Ready-mix plants sell in fixed steps and many have a minimum load, so round the figure up to whatever increment your supplier quotes. Ask them when you call; it changes the last fraction of a yard, not the size of the job.
Footings and piers
Long narrow pours are easier to think about per length of trench. With 10% waste:
| Footing width × depth | Yards per 10 ft | Yards per 100 ft | Feet of footing per yard (no waste) |
|---|---|---|---|
| 12 × 8 in | 0.27 | 2.72 | 40.5 |
| 16 × 8 in | 0.36 | 3.62 | 30.4 |
| 16 × 10 in | 0.45 | 4.53 | 24.3 |
| 20 × 10 in | 0.57 | 5.66 | 19.4 |
| 24 × 12 in | 0.81 | 8.15 | 13.5 |
Footing sizes for a house or an addition are set by your local building code and soil, so use these rows to estimate volume once you know the required size, not to choose it.
Deck and porch piers poured in round tube forms are small, so they are usually bought in bags. Each row is one pier with 10% waste; "piers per yard" is useful if you are pouring many from a truck.
| Tube diameter × depth | Cu ft per pier | 80 lb bags per pier | Piers per cubic yard (no waste) |
|---|---|---|---|
| 8 × 36 in | 1.15 | 2 | 25.8 |
| 8 × 48 in | 1.54 | 3 | 19.3 |
| 10 × 36 in | 1.80 | 3 | 16.5 |
| 10 × 48 in | 2.40 | 4 | 12.4 |
| 12 × 36 in | 2.59 | 5 | 11.5 |
| 12 × 48 in | 3.46 | 6 | 8.6 |
| 16 × 36 in | 4.61 | 8 | 6.4 |
| 16 × 48 in | 6.14 | 11 | 4.8 |
| 18 × 48 in | 7.78 | 13 | 3.8 |
Pier depth must reach below the frost line where you live, so 48 in rows are common in cold climates. If you also need posts, rails and pickets, the fence calculator counts the post concrete with the rest of the fence.
Worked example: a garage slab with a thickened edge
A 24 × 24 ft garage slab, 4 inches thick, with a thickened edge around the outside: a strip 12 inches wide where the slab goes down to 12 inches deep, so 8 inches below the main slab. The edge size here is only an example; your plans or inspector set the real one.
- Main slab: 24 × 24 × 4 ÷ 12 = 192 cubic feet.
- Edge strip area: the outer 24 × 24 square minus the inner 22 × 22 square = 576 - 484 = 92 sq ft. Using the outside perimeter (96 ft) would count the four corners twice.
- Extra edge concrete: 92 sq ft × 8 ÷ 12 = 61.3 cubic feet. In the calculator this is the footing shape: 92 ft long, 12 in wide, 8 in deep.
- Total: 192 + 61.3 = 253.3 cubic feet, or 9.38 cubic yards with no waste.
- Add 10%: 278.7 cubic feet, which is 10.32 cubic yards. With 5% it would be 9.85.
So the thickened edge alone adds 2.27 yards before waste (2.5 with it), about a third more than the flat slab. Order about 10.5 yards, or round up to your supplier's next step. By hand it would be 465 bags of 80 lb mix, which is why nobody bags a garage floor.
What changes the answer
- Thickness. On a 20 × 20 ft slab, 4 inches needs 5.43 yards and 6 inches needs 8.15. Two inches more means 50% more concrete.
- Low spots in the base. A base that sits 1/4 inch low across a 20 × 20 slab takes 0.31 extra yards, 1/2 inch takes 0.62 and 1 inch takes 1.23. On a 4 inch slab, 1/2 inch low is 12.5% more concrete, more than the whole waste allowance.
- Waste allowance. For a 24 × 24 × 4 in slab, 5% gives 7.47 yards and 10% gives 7.82. The 0.35 yard gap is cheap insurance next to a short load.
- Thickened edges, footings and haunches. As the garage example shows, they can add a third to a slab order and are easy to forget.
- Bags or truck. With the calculator's example prices, 45 bags at $6.50 cost $292.50 for one yard of concrete, against $165 for a yard of ready-mix. A 10 × 10 × 4 in patio (1.36 yards) is 62 bags for $403, against $224 of ready-mix before any delivery or short-load fee. Small orders often carry those fees, so get the real quote before you buy 60 bags. Our bags of concrete guide has bag counts for slabs and fence posts.
Common mistakes
- Dividing by 27 too early or not at all. Work in cubic feet, then divide by 27 once at the end.
- Using nominal lumber sizes. A slab formed with 2×4s on edge is 3.5 inches deep, not 4. Ordering for 4 inches gives about 14% extra, which is fine if you meant to, and a surprise if you did not.
- Leaving out the base. A slab needs a compacted gravel base below it, ordered separately. The gravel calculator works out the tons.
- Counting perimeter corners twice when you estimate a thickened edge or a footing around a square, as shown in the worked example.
- Ordering exactly the computed number. A truck that runs short leaves a cold joint, and a second short load usually costs more than the extra half yard would have.
Try the concrete calculator
Enter your own numbers below, or open the full concrete calculator with the formula and more examples.
This guide is general information with example numbers, not financial, tax or building advice. Your costs and results will differ. Terms
Frequently asked questions
How many square feet does a yard of concrete cover?
At 4 inches thick, one cubic yard covers 81 sq ft. At 5 inches it covers 64.8 sq ft and at 6 inches 54 sq ft, before any waste allowance.
How many yards of concrete do I need for a 24x24 garage?
About 7.1 cubic yards for a 4 inch slab, or 7.8 with 10% waste. At 6 inches it is about 11.7 yards with waste. A thickened edge 12 inches wide and 8 inches deeper adds about 2.3 yards more before waste.
How many yards of concrete for a 12x12 slab?
A 12x12 slab at 4 inches thick needs 1.78 cubic yards, or about 1.96 with 10% waste. At 6 inches it needs about 2.93 yards with waste.
How do I calculate yards of concrete?
Multiply length by width in feet, multiply by the thickness in inches and divide by 12 to get cubic feet. Add your waste allowance (usually 10%), then divide by 27 to get cubic yards.
How many yards of concrete for a 100 ft footing?
A 16 inch wide, 8 inch deep footing takes about 3.6 cubic yards per 100 ft with 10% waste. A 20 by 10 inch footing takes about 5.7 yards.